The goal: Build a room to house an advanced
medical device.
The condition: Don’t make a sound while you’re doing
it.
“Hospital construction and reconstruction is
unique,” says Steve Pacini, a project manager at San
Francisco-based Herrero Construction Co. “There are
so many variables that things can get crazy.”
Even though he’s Herrero’s go-to guy for managing
projects that others don’t want to touch — ORs,
ICUs, asbestos removal — Pacini, a 27-year veteran
of hospital construction, doesn’t use words like
“crazy” casually. But in this case he’s referring to
a recent construction job he oversaw at the
University of California San Francisco, a teaching
hospital that ranks among the top 10 U.S. medical
centers.
The project, which exploded in complexity,
originally started as a small refurbishing job at
UCSF’s cardiac department. But that changed when the
university decided to install a Stereotaxis unit, a
machine that uses two powerful 4-ton magnets to pull
a catheter through a heart patient’s circulatory
system. Because the machine, which is remotely
controlled, can pull the catheter perfectly through
the center of a vein or artery, avoiding scrapes
with plaque or walls, it considerably lessens the
procedure’s risk and length.
For UCSF, installing the Stereotaxis would be a
coup: It would be the first unit of its kind on the
West Coast, adding an ultra-sophisticated new tool
to a cardiac unit already acknowledged as one of the
nation’s best.
But there was a rub. The Stereotaxis magnets were
so powerful that they would have to be completely
shielded. With MRI machines located only two floors
below, it was crucial that no magnetic fields
whatsoever leak out and cause distortions. Pacini
would have to oversee the construction of a room
within a room, cloaking a 600-square-foot space in
layers of siliconized steel. It was a type of
construction that nobody on the West Coast had ever
undertaken.
There was a second rub – one that turned an
already complex project into a seemingly impossible
one. The space that would accommodate the
Stereotaxis unit is wedged between the pediatrics
ward above and the hospital’s heart, kidney and vein
transplant ORs below. UCSF made it clear that there
could be no noise during construction, even though
Pacini’s crew would have to tear out one side of the
building’s fifth floor to begin work.
“We had to invent and develop a slew of
anti-noise methods,” says Pacini, “including quiet
drills, and anything and everything to lessen or
eliminate the sounds made by dropping studs,
hammering, shooting staples and all the other noises
construction creates.”
Pacini’s crew came through. Susan Grizzle, RN,
who manages the Stereotaxis and other diagnostic
equipment on the fifth floor, says that there were
only three occasions over the life of the project
when she received minor complaints about noise from
the construction. “I personally never heard a sound.
I still don’t know how they did it.”
What was originally estimated to be a four-month
project eventually stretched out to almost a year.
Because Herrero had to invent building methods as it
went along, the company insisted that UCSF make the
project timeline open-ended. Aware that Herrero had
30 years of experience in hospital construction,
much of it on the UCSF campus, the university
agreed.
“Every day was a learning curve,” says Pacini.
“The room was so small there was no place for
storage, so we had to move materials back and forth
constantly.” There was also the health threat posed
by siliconized steel dust, which required crew
members to wear respirators and eye protection in an
often stiflingly hot space. “We soon got a rhythm.
Still, some people quit and we wound up with
basically a Herrero crew. Because we’d all worked
together before, we were able to weather the
challenges pretty well.”
The focus of the crew’s efforts were
4-foot-x-8-foot sheets of siliconized steel
sheeting, each .032 inches thick. “They were razor
sharp, but fortunately we suffered only two cuts on
the job,” says Pacini. The workers installed a total
of 12 layers of the sheeting to create a 3/8-inch
shield around the space where the Stereotaxis would
eventually sit. They laid four layers at a time,
criss-cross. Since each square foot of the material
weighed 32 pounds, the men had to use jacks to help
them lift the sheets into place.
“First we built a firewall, then a secondary
wall, to which sheets were attached. Where sheets
joined, the gaps could be no greater than 2
millimeters. It was easy to build the walls, but
when we got to the ceiling, it needed
reinforcement.”
Pacini says the work was tedious and painstaking,
“especially lining up drill holes for ceiling and
floor anchors — we had to use laser templates to do
this. Also, we had to run conduits in a tight crawl
space between the top of the installation and the
sixth floor. We surrendered many weekends to get
this done. We had started working regular eight-hour
days, five days a week, then quickly ramped up to
nine hours a day, six days a week.”
When the job was complete, the crew received a
letter from a Stereotaxis executive who commented
that his company had never seen such a perfect
installation. “It was a great morale booster. We
were spent; we’d been on the job for over a year.”
Today, all of his crew’s shielding work lies
hidden behind a nondescript light beige wall,
colored the same as all the rooms and corridors on
the rest of the floor. Unless somebody tells you
otherwise, you don’t know it’s there.
Looking back, Pacini, no stranger to tough tasks,
says, “If I were to rate this job from 1 to 10, 10
being the most difficult, it was definitely a 10.”